There are instances where rate changes when certain number of mileage are met. Here’s where Sub-rate comes in. Administrators can add the sub-rate based on country or vehicle group per year/expense.

To add sub-rate per main mileage rate

  1. Go to Admin > Mileage > Choose the existing mileage rate.
  2. Click Add Sub rate button.
  3. Fill in required fields. Once done, Click Save

To add Sub Rate per vehicle group.

  1. Click Add Mileage Rate of Existing rate.
  2. In Vehicle Group field, click (+) icon.
  3. Add vehicle group page appears.
  4. Click Edit button
  5. Click Add Sub rate
  6. Enter required information.

7. Click Save.

Note: Rydoo calculate the mileage rates by fiscal year that was set up in the Branch, so the sub rates will be calculated accordingly. The Fiscal date can be set up under the Branch tab.